Mettur Thermal Power Station is situated in Salem District.
This is the first inland thermal Power Station of TANGEDCO.
The first stage consists of units I & II of 210 M.W at a cost of Rs. 384.30 crores
.
The second stage consists of units III &IV of 210 M.W each at a cost of Rs.351.76 crores.
All the four units are coal based.
Stage
|
Unit
|
Continuous
| ||||||
running in days
| ||||||||
Station
|
71
| |||||||
I
|
I
|
227
| ||||||
II
|
205
| |||||||
II
|
III
|
272
| ||||||
IV
|
311
| |||||||
Name & Address
|
Stage
|
Unit
|
Capacity(M.W)
|
Date of
| ||||
Commissioning
| ||||||||
Mettur T.P.S,
|
I
|
I
|
210
|
07/01/1987
| ||||
Metturdam,
|
II
|
210
|
01/12/1987
| |||||
Salem(District),
|
II
|
III
|
210
|
22/03/1989
| ||||
PIN:636406.
|
IV
|
210
|
27/03/1990
| |||||
Phone No. 04298 -240390
| ||||||||
Fax No.
|
04298 -240011
| |||||||
e mail :cemtps@tnebnet.org
|
AWARDS AND ACHIEVEMENTS
• MTPS has received cash awards along with shields, Medals & Certificates from the Govt of India for higher Productivity, Reduction in Auxiliary Consumption, Reduction in fuel Oil Consumption when the cash incentive reward scheme by the Govt. of India was in force.
• MTPS has received Gold Shield under Government of India meritorious productivity Reward scheme for 4
years consecutively during 2000-2001, 2001-02, 2002-03,2003-04 for peak hour generation.
• Under the modified comprehensive Performance award scheme by the Govt. of India from the year 2004-05, MTPS has been awarded Bronze shied for the year 2005-06.